Another slice of salami, anybody?

In February 2023, the Court of Appeal overruled an earlier High Court decision (December 2022) in relation to the ‘Tewkesbury bridge’. Tewksbury Borough Council had granted planning permission for the bridge over a railway near Ashchurch in March 2021, but this was challenged by Ashchurch Rural Parish Council.

The officer’s report to the council’s planning committee had highlighted the benefits of the bridge. Its principal function was to provide access to the site of a future residential development. The report advised that the harms associated with the future housing development should be disregarded and that the concerns raised locally about future development plans that would be enabled by the bridge were not material to the decision. The screening decision considered the bridge as a stand-alone project and ignored the housing development that it was intended to facilitate, concluding that the bridge was not likely to have significant effects and that EIA was not necessary.

The Court of Appeal concluded that the planning committee had acted irrationally by weighing the benefits of the wider development without considering the harms.

Lady Justice Andrews warned that the objectives of the EIA Regulations must not be avoided by subdividing a single project into separate parts. Similar earlier judgements called the process ‘salami-slicing’.

The ruling re-affirms the importance of giving careful consideration to the extent to which works and activities for which planning consent is sought form part of a larger project.

In practice, later parts of a wider project may not be sufficiently designed to allow a fully detailed EIA. The judgement, however, suggests that best efforts must be made to define and assess the full scope of the project and the likely activities and environmental effects, perhaps through a likely worst-case cumulative assessment, to allow the decision maker to weigh the impacts of a project against its benefits properly.

What’s the outcome?

We have been waiting for some time to see whites of the Government’s eyes following indications of a new vision for impact assessment. Well, that may still be concealed behind the anti-glare sunglasses but now at least we have some further indications of the way that EIA may be going.

Part 5 of the Levelling Up and Regeneration Bill (May 2022) proposes an “environmental outcomes” process to replace SEA and EIA, and an Environmental Outcomes Report will become the new Environmental Statement. These will be needed to gain consent for some plans and projects, and the outcomes will be measured against nationally set environmental targets. Tangible, simple and joined up, apparently. Time will tell. At least the Bill as drafted requires the Secretary of State for Levelling Up to ensure that the new process will at least maintain the level of protection afforded by that it replaces.

High Court quashes EIA screening direction

 

The High Court has quashed the Secretary of State for Housing, Community and Local Government’s screening decision that EIA was not required for a proposal to develop 20 houses on the site of a rendering plant in the Kent Downs Area of Outstanding National Beauty that was formerly one of the main areas used to dispose of slaughtered cattle infected with BSE during the 1990s.

While the Secretary of State had identified that BSE-related contamination required further investigation, no expert evidence on the issue, relevant risk assessment or details of any possible remediation measures were provided with the application.

As such, the High Court ruled that the Secretary of State had not been in a position to make an informed judgment about whether remediation would be possible, and this should not simply have been assumed. A similar error in law was made in an earlier case, Gillespie v the First Secretary of State, 2003. 

High Court quashes permission for energy storage facility due to EIA errors

The High Court recently announced its decision in the case of R. (on the application of Kenneth Ross) v East Hampshire District Council and Anesco Limited.

Anesco had applied for planning permission to install two energy storage systems with a total capacity of 49.95MW together with associated infrastructure at Lovedean, north of Portsmouth and just to the south of the South Downs National Park.

A local resident claimed that East Hampshire District Council’s consideration of the proposal was flawed, but planning permission was nonetheless granted. The resident sought judicial review on a number of grounds.

The High Court found that the Council had wrongly concluded that the development was not ‘major development’, that the application was therefore unlawfully validated, and that it had failed to require an EIA or to take it into account.  In particular, the Court ruled that the decision failed to take proper account of the cumulative impact of the proposals, contrary to Schedule 3, paragraph 14 of The Town and Country Planning (Environmental Impact Assessment) Regulations 2017. 

SNH publishes draft guidance on wind farm repowering EIA

SNH's draft guidance, ‘Assessing the impact of repowered wind farms on nature’ (Consultation draft, June 2018) was published recently following its launch at the Scottish Renewables Onshore conference. The consultation period closes on 31 August.

The most contentious element is probably SNH’s position that the baseline adopted for the EIA should ignore the existing wind farm. The industry is expected to maintain its stance of opposition on this issue.  The brief document also includes sections on assessments relating to visual effects, birds and other ecology. 

The guidance is available at: https://www.nature.scot/guidance-assessing-impact-repowered-wind-farms-nature-consultation-draft-june-2018

 

SNH.jpeg

New advice on Strategic Environmental Assessment published

The RTPI has published new practice advice to help UK planners undertaking SEA. The aim of the note is to help identify ways of finding a focus for the SEA to increase the quality of analysis and presentation. The note is based on European and UK Government guidance and applies across the UK. It works through the key components and processes of SEA and Sustainability Assessment, highlighting good practice and case studies.

The document is available to download from here:

http://www.rtpi.org.uk/media/2668152/sea-sapracticeadvicefull2018c.pdf

 

EU Guidance updates

The European Commission has updated and revised its three EIA Guidance Documents that look at EIA screening, EIA scoping, and the preparation of the EIA report. The updates reflect good practice and legislative changes since the publication of the original guidance documents in 2001.

The documents provide insight to practitioners, developers, decision-makers and others involved in EIA, drawing from experiences and lessons across the world. They are available to download from the EU website.

Screening:

http://ec.europa.eu/environment/eia/pdf/EIA_guidance_Screening_final.pdf

Scoping:

http://ec.europa.eu/environment/eia/pdf/EIA_guidance_Scoping_final.pdf

Preparing the EIA Report:

http://ec.europa.eu/environment/eia/pdf/EIA_guidance_EIA_report_final.pdf

EU.jpeg

English 2017 EIA Regulations published

The UK Government has completed the transposition of the revised EIA Directive into domestic law.  The Town and Country Planning (Environmental Impact Assessment) Regulations 2017 were laid before Parliament on 19 April 2017, just before the purdah period for the General Election.  They come into force on 16 May 2017.

There had been a fear that the Government would miss the deadline for the transposition of the Directive because of the surprise General Election announcement and the restrictions that come with it.

The completely new Regulations introduce new requirements into the EIA process, as well as bringing changes to the content of environmental statements. 

They are available at: http://www.legislation.gov.uk/uksi/2017/571/introduction/made